Duferco La Louvire, Belgium, on the run modules for supply chain optimization
Apr 30, 2009
Duferco La Louvire, part of Duferco Group, has finished implementing two modules for the optimization of its supply chain, complementing the existing SteelPlanner environment.

The first additional module is BetaMatcher MidTerm for the optimal hot strip mill coffin selection. To efficiently manage a HSM, the planning department always has to tackle two complex and consecutive problems: the assignment of slabs to orders and the scheduling of those assigned slabs. Traditionally, these two logistical problems are solved independently. However, this way of working is suboptimal and implies some drawbacks. This might result in assigned slab populations that are not feasible to schedule or that result in poor schedule quality. Shortcutting those issues, the implementation of BetaMatcher at Duferco La Louvire solves the assignment problem and the HSM Scheduling critical constraints in one optimization round.

Mr. Tufaru, planning manager at Duferco told STEEL GRIPS: "BetaMatcher MidTerm added value to the slab utilization process and allowed us to maximize the HSM schedules by assigning the critical sizes which increased the schedule length up to 15%."

The second module is MFC-CAP for capacity planning and due date quoting. MFC, AIS' leading solution for profit optimization, capacity planning and master scheduling, has been implemented and tuned in order to face the challenging production environment of Duferco La Louvire. Constraints like casting transition rules, product mix at the hot strip mill, different production routes with possible reparation operations, campaigns at the pickling lines, limited inventory storage capacity, customer orders due date, complex shipment constraints and different priorities for different order categories have been accurately modeled in the system.

Mr. Havelange, project manager at Duferco says: "That project allows us to control efficiently the flow and to forecast problems. It gives us clear and feasible production plan which is a base for strategic discussions and decisions."

Since the go-live in July 2008, the improvements brought by BetaMatcher appeared very quickly: the weight and the length of the sequences of rolled slabs have increased by an average of 15% to 20%.

On the other hand, MFC has improved the customer service and cross line synchronization. Moreover, within the current economical situation, MFC has been extensively used in order to simulate different production scenarios in order to plan line maintenances and shutdowns.


In addition, make sure to read these articles:
read also Duferco La Louvire, Belgium, on the run modules for supply chain optimization
read also Capacity planning optimization and campaign planning for Duferco La Louvire
read also First European order for parsytec 5i

toptop of page   back back   send this news to a friend Tell a friend    printerfriendly page print   read read times  

© 2009 GRIPS Intermedia GmbH All rights reserved. Reproduction in whole or in part without permission is prohibited.
 
- advert -
subscribe to Steel-Grips
LINKING STEEL SELLERS AND BUYERS IN THE MIDDLE EAST
steelgroup
custeel

no external All external sites will open in a new browser.
GRIPS media does not endorse external sites.