NLMK restarts blast furnace #2 and #3
Feb 18, 2009
update NLMK has put its blast furnaces (BF) #2 and #3 into normal operation.

The furnace #3 in the Lipetsk works has a maximum production capacity of 1.3 million t/a of pig iron. BF#3 was idled for a general overhaul in October 2008.
 
As part of the 100-day overhaul of the 2,000 m³ unit, the furnace shell and cooling system were partially renovated and the refractory was fully relined. The overhaul cost was RUR65 million.

The 1000 m³ blast furnace #2 which with a total capacity of 700,000 t/a underwent a 100-day overhaul.

The annual pig iron capacity at the Lipetsk production site will reach 7.9 million tonnes, and steel-making capacity utilization will reach 87%.





In addition, make sure to read these articles:
read also NLMK revamps its melt shop
read also NLMK completes installing equipment at new power plant
read also NLMK's Kaluga mini-mill, Russia, to install production facilities
read also VIZ-Stal, Russia, to implement new planning system
read also NLMK upgrading hot rolling mill
read also NLMK commissions new hot-dip galvanizing line
read also NLMK restarts blast furnace #2 and #3
read also NLMK, decommissions another two coke batteries
read also Dedusting facilities for new LD steelmaking converter at Novolipetsk Steel (NLMK), Russia
read also Novolipetsk Steel idles two blast furnaces

toptop of page   back back   send this news to a friend Tell a friend    printerfriendly page print   read read times  

© 2009 GRIPS Intermedia GmbH All rights reserved. Reproduction in whole or in part without permission is prohibited.
 
- advert -
subscribe to Steel-Grips
LINKING STEEL SELLERS AND BUYERS IN THE MIDDLE EAST
steelgroup
custeel

no external All external sites will open in a new browser.
GRIPS media does not endorse external sites.